You will build a Bill of Quantities sheet that lists every measured item with its unit, quantity and rate, so contractors price the same scope. It suits students, estimators and project managers pricing a construction job. You need the drawings and the standard method of measurement your contract names.
YouTube video: Bill of Quantities Explained: How to Make a Bulletproof BOQ Sheet
Captions are available. Use CC in the YouTube player.
- Video length
- 10 min 8 s
- Time to do it
- 3 hours
- Difficulty
- Medium
- Steps
- 8
What you need
Steps
Pick the standard method of measurement your project uses, such as SMM7, NRM2 or CESMM4, and confirm the client or contract requires it before you measure anything.
Open a spreadsheet and set up six columns: item number, description, unit, quantity, rate and amount. Add a header with the project name, date and revision number.
Work through the drawings trade by trade. Measure each item once, enter the quantity in the unit the method of measurement asks for, and note the drawing sheet and grid reference.
Write each description so it states what is included and excluded, for example concrete to foundations excluding formwork. Keep the wording in the same order as the standard method.
Enter rates in the rate column and let the sheet multiply quantity by rate to fill the amount column. Check a few rows by hand.
Add a preliminaries section for site setup, supervision, insurance and temporary works, priced separately from the measured work.
Add prime cost sums for items you will buy later at a known price and provisional sums for work you cannot measure yet, and label each one clearly.
Total each trade, then total the whole sheet. Cross-check the quantities against the drawings one more time before you send it out.
Tips and common mistakes
Leave the rate column blank on the version you send to tenderers so they price it themselves.
Round quantities the same way throughout and always state the unit, because mixing metres and millimetres causes expensive errors.
Number every item so bidders can quote and query a specific line.
Keep a revision log. A changed drawing should produce a new BOQ revision, not a quiet edit to the old file.
Questions
What are the six columns of a Bill of Quantities?
Item number, description, unit, quantity, rate and amount. Some firms add a remarks column for drawing references.
What is the difference between a prime cost sum and a provisional sum?
A prime cost sum covers work or materials bought later at a known price from a named supplier. A provisional sum is an allowance for work you cannot measure yet.
Can I build a Bill of Quantities in Excel?
Yes. A plain spreadsheet with the six columns, a total row and a revision header is enough for small projects.